ZORBAZ PROJECT | DETROIT LAKES, MN

This project included combining two kitchens into one new kitchen addition and new exterior features to include a standing seam roof.  A new temporary kitchen had to be constructed in order to construct the new kitchen.  Mechanicals [electrical, plumbing and gas lines] had to be disconnected and temporarily re-routed for the new kitchen.  After the new kitchen was complete, the temporary kitchen was dismantled. All this construction was done while keeping the restaurant in business without closing.